Prevention of ground subsidence through excavation work
Last update date April 1, 2024
1.Excavation scale to be notified (Article 114 of the Ordinance (Article 77 of the Enforcement Regulations))
- Drilling work: The excavation depth is 4 meters or more below the ground surface and the excavation area is 500 square meters or more
- Tunnel construction: Finished inner diameter of 1.35 meters or more and extension of 100 meters or more
Pamphlet (land subsidence and excavation work-regulation by excavation work-) (PDF: 301KB)
Notes
- The excavation area of the excavation work shall be the projected area.
- The extension of tunnel construction includes shafts.
- If the tunnel shape is other than a circular shape, it is applicable if any of the completed cross-sectional shape of the tunnel is 1.35 meters or more.
2.Details of notification
About the following reports, we can perform in Yokohama-shi electronic application, report service (outside site).
1.When drilling work (Related to Article 117 of the Ordinance)
registration form (No. 29 style) (Word: 16KB)
Guide (Creation of excavation work in registration form) (PDF: 789KB)
Businesses that fall under the above excavation scale (construction contractor) must notify us at least 30 days before the start of the excavation work (in the case of excavation).
Details of the notification and attached documents
- Name or name and name of representative in case of Address and corporation
- Location where drilling work is performed
- Outline of drilling work (excavation area, drilling depth, construction type and construction method, construction period of underground part)
- Other matters specified by rules (measurement plan for changes in the surrounding ground, excavation floor plan, excavation cross section, excavation longitudinal section)
- attached documents A) Guide map, (a) soil survey materials, c) structure outline, construction) Reason for selection of excavation method (including auxiliary method), o) process schedule
Notes
- In the measurement plan for changes in the surrounding ground, etc., describe the measurement items, frequency, location, management standards, management system, and response in case of abnormality.
- "Excavation method" refers to the method of retaining the mountain in the case of excavation work, and the method of excavation (shield, NATM, propulsion method, etc.) for tunnel work.
- "30 days before the start of excavation work" refers to the earlier of the construction of a retaining mountain or digging up the ground.
2.When making changes (Related to Article 118 of the Ordinance)
Drilling work change registration form (No. 30 style) (word: 28KB)
- Changed to the contents of the notification and item 1 of attached documents: Please notify us within 30 days from the date of the change.
- Changes to the contents of the notification and items 2 to 4 in attached documents: Please notify us at least 30 days before the date of the change.
3.When drilling work is completed (Related to Article 120 of the Ordinance)
Completed drilling registration form (No. 31 style) (word: 13KB)
When the excavation work is completed, please notify us within 30 days from that date.
3.Notes on excavation work (Related to Articles 115 and 119 of the Ordinance)
Guidance standards for prevention of ground subsidence by excavation work
- When planning excavation work, select a construction method that has high water stopability and minimizes the impact on the surrounding ground and groundwater level.
- If there is a risk of collapse of the ground, collapse of the ground surface or subsidence during excavation work, select an appropriate auxiliary method in advance to stabilize the ground.
- During excavation work, try to detect abnormalities not only in the excavation premises but also in the surrounding ground and structures at an early stage, and observe groundwater levels, ground changes, etc. (Please keep the recording of variable observations for 3 years.)
- In the event that land subsidence occurs due to the excavation work, take necessary measures, including temporary suspension of construction.
4.Guidance, advice, and recommendations (Related to Article 116 of the Ordinance)
The mayor may provide necessary guidance and advice to businesses that perform excavation work to prevent land subsidence, and recommend that necessary measures be taken when there is a risk of land subsidence (when it occurs). There is.
You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
Inquiries to this page
Water and Soil Environment Division, Environmental Conservation Department, Yokohama City Green Environment Bureau
Telephone: 045-671-2494
Telephone: 045-671-2494
Fax: 045-671-2809
Email address: mk-dojo@city.yokohama.lg.jp
Page ID: 981-131-309