73.(tentative name) Yokohama-sta.-nishiguchi station building plan (JR Yokohama Tower, JR Tsuruyacho, Yokohama building) environmental assessment procedure

Last update date April 24, 2020

List of procedure situation
Business name (tentative name) Yokohama-sta.-nishiguchi station building plan (JR Yokohama Tower, JR Tsuruyacho, Yokohama building)
Conduct area 1-1-1, Minamisaiwai, Nishi-ku, Yokohama-shi extra
Business type Construction (targeted for the regulations) of high-rise
Company East Japan Railway Company., Tokyu
Method book

Submission: August 26, 2010
Notification, general inspection: From September 3, 2010 to October 18, 2010

Ward that is targeted for general inspection Kanagawa Ward, Nishi Ward
Statement of position tsusuu: Nine of them
Examination committee

Question: September 6, 2010
Report: December 14, 2010 (PDF: 231KB)

Method statement of position (PDF: 255KB)

Making: December 28, 2010
Notification, general inspection: It is February 14, 2011 from January 14, 2011

Brief

Submission: March 11, 2011
Notification, general inspection: It is May 9, 2011 from March 25, 2011

Ward that is targeted for general inspection Kanagawa Ward, Nishi Ward
Briefing session

The date: April 20, 2011, April 23 (twice in total)
Participant: A total of 217 people

Statement of position tsusuu: Three of them
Opinion statement Report: 0 people
Evaluation book

Submission: August 1, 2011
Notification, general inspection: It is September 13, 2011 from August 15, 2011

Ward that is targeted for general inspection Kanagawa Ward, Nishi Ward
Statement of position tsusuu: Two of them
Examination committee

Brief question: April 5, 2011
Evaluation book question: September 6, 2011
Report: November 17, 2011 (PDF: 372KB)

Examination book (PDF: 285KB)

Making: November 22, 2011
Notification, general inspection: It is January 4, 2012 from December 5, 2011

Report

Submission: December 12, 2011
Notification: December 22, 2011

Start registration form

Report: December 27, 2011
Start: January, 2012

Subsequent investigation plan
(during construction)

[the dismantling construction] (PDF: 1,809KB)
Submission: 25, Heisei nine a month three days a month
Notification: September 13, 2013
[new construction] (PDF: 2,009KB)
Submission: September 14, 2015
Notification: October 5, 2015

Subsequent findings report
(during construction)

[the dismantling construction] (PDF: 2,112KB)
Submission: February 14, 2014
Notification: February 25, 2014
[new construction]
Submission: November 11, 2019
Notification: November 25, 2019

Completion registration form Report: April 1, 2020
In-service start registration form Report: April 1, 2020
Subsequent investigation plan
(after the service)

Submission: April 1, 2020
Notification: April 24, 2020

Subsequent findings report
(after the service)
Undecided

Adobe Acrobat Reader DC (old Adobe Reader) is necessary to open file of Portable Document Format.
Person who does not have can download free of charge from Adobe company.
Get Adobe Acrobat Reader DCTo downloading of Adobe Acrobat Reader DC

Inquiry to this page

Environmental Planning Bureau policy coordination department environmental assessment section

Telephone: 045-671-2495

Telephone: 045-671-2495

Fax: 045-663-7831

E-Mail address [email protected]