Self-financed construction of roads

Last Updated August 27, 2019

What is road self-financing construction?

When a person other than the road manager performs construction about the road, it must be approved by the road manager. (Article 24 of the Road Law)

Application for main road self-financing construction

•Decrease of sidewalks, L-shaped and curbs for vehicles
•Relocation or removal of car stoppers and tree-planting basins
•Relocation of curved mirrors, street trees, etc. (Telephone poles are licensed by Tokyo Electric Power Company)
•Decrease work for setting up designated roads
•Repair and restoration of damaged pavement
•Road maintenance associated with development and residential land development
•In addition, when it is necessary to change the road structure

Documents to be submitted

○Application for approval of road construction, etc. (Attach the following materials attached, 2 copies each)
<attached documents>
•Guide map (a house map, etc. that shows the application site)
•Floor plan (construction site and enforcement details are shown in a way that shows the entire site)
•Vertical cross section
•Photographs of current status
•Specimens of structural drawing
•Copy of road ledger floor plan
•Copy of road ledger area map or road boundary survey map (available in Public Works Office)
•Copy of official map (not required because it is for reference only)
Application form download
When making an application, please refer to the "Guide to Road Self-financing Construction".

Flow of self-financing construction procedures

After submitting the application form, an approval letter will be issued after a field survey by the road manager. After issuing the approval letter, registration form will be submitted and the construction will be carried out. Upon completion, submit a notification of completion (including guide map, construction and photographs during construction and completion) After the inspection by the road manager, a letter of acceptance is issued and it is completed.
Note 1 - During construction includes construction work management photos.
Note 2 - Report between actual measurement boundary points in the boundary survey map (road ledger map) (filled in red letters)

For inquiries to this page

Hodogaya Ward Hodogaya Public Works Office

Phone: 045-331-4445

Phone: 045-331-4445

Fax: 045-335-0531

Email address: ho-doboku@city.yokohama.jp

Return to the previous page

Page ID: 963-906-966

Menu of ward

  • LINE
  • Twitter
  • Instagram
  • YouTube