About road self-financing construction

Last Updated October 30, 2024

What is road self-financing construction?

When person except road manager performs construction or maintenance about road, it must receive approval of road manager (Road Law Article 24). Because the cost required for this construction is to be borne by the approved person (Article 57 of the Road Law), it is commonly called "own expense construction".

Main road self-financing construction

After construction is completed, the road manager will manage it, so you will have to maintain it at the same level as when the road manager constructs it.
The main contents of the construction are as follows.
・Drawing and cutting of sidewalks
・Relocation or removal of street trees and tree-planting basins
・Relocation or removal of protective fences
・Relocation of curved mirrors, lighting, etc.
・Relocation of signs, etc. (managed by road managers)
・New construction and improvement of gutters
・Other construction related to roads

Application for road self-financing construction

After confirming guide (PDF: 994KB) in enforcement approval application such as road construction, fill in required items, attach the following drawings, and submit two copies. (Download the form after the application form)
If the application is incomplete (missing or missing attached books), the application will not be accepted.
It takes a certain number of days from receipt of the application to approval, so please apply in time according to the construction schedule.
Attached books
Please attach the following drawings to the application form.

  • Guide map (Please attach one with no copyright or other problems)
  • Floor plan (Please illustrate the construction site and construction details so that the entire site can be understood)
  • Vertical cross-section (Please create a drawing that shows the slope, height difference, etc. according to the construction details)
  • Structural diagram (drawings that show structures such as pavements and gutters)Road Structure Standard Maps"(City of Yokohama, Road and Highway Bureau),"Yokohama-shi sewer design standard figure (tube)Please refer to "(Yokohama City Sewerage River Bureau))
  • Photograph of the current situation (Please attach a distant view and near view that shows the local situation)
  • Copy of road ledger area map or copy of boundary investigation figure such as road waterway (please attach copy of any drawing. A copy of the road ledger area map can be obtained in Public Works Office if the drawing is created.Yokohama no Michi (outside site)You can check it. In addition, a copy of the boundary survey map for roads and waterways can be obtained at Public Works Office if a boundary survey is conducted.)

Flowchart of self-financing procedures
Procedures for self-financing construction

About application, please download "enforcement approval application such as road construction" after application style.
Please download "Various notifications [Start / Change / Cancellation / Completion] after approval" after the application form for the start notification / completion notification.

You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

Inquiries to this page

Totsuka Ward Tozuka Public Works Office

Telephone: 045-881-1621

Telephone: 045-881-1621

Fax: 045-862-3501

Email address: to-doboku@city.yokohama.lg.jp

Return to the previous page

Page ID: 981-184-655

Menu of ward

  • LINE
  • Twitter
  • Instagram
  • YouTube