What is road self-financing construction?

When person except road manager performs construction or maintenance about road, it must receive approval of road manager (Road Law Article 24). The cost required for this construction is to be borne by the person who has been approved (Article 57 of the Road Law), so it is commonly referred to as "own expense construction".

Main road self-financing construction

After the construction is completed, the road manager will manage it, so you will have to maintain it at the same level as when the road manager works.
The main contents of the construction are as follows.
・Decrease and round-up of sidewalks
・Relocation or removal of street trees and tree-planting basins
・Relocation or removal of protective fences
・Relocation of curved mirrors and lighting
・Relocation of signs, etc. (those managed by the road manager)
・Construction and improvement of gutters
・Other road construction

Application for self-financing construction

After confirming the guide (PDF: 994KB) on the enforcement approval application for road construction, fill in required items, attach the following drawings, etc., and submit two copies. (Please download the form from the application form.)
If the application form is incomplete (missed or missing attached documents), the application will not be accepted.
It takes a certain number of days from receipt of the application form to approval, so please apply in time according to the construction schedule.
Attached books
Please attach the following drawings to the application form.

  • Guide map (Please attach a copy that does not have any problems with copyright etc.)
  • Floor plan (Please show the construction site and construction details so that the entire site can be understood.)
  • Vertical cross section (Please create a drawing that shows the slope, height difference, etc. according to the construction content)
  • Structural diagram (drawings that show the structure of pavement and gutters ("Drawing)Road Structure Standard Map"(City of Yokohama, Road and Highway Bureau)," Yokohama City Sewerage Design Standard Map (pipe) "(Yokohama City Sewerage and River Bureau)
  • Photos of the current situation (attach a distant view that shows the local situation)
  • A copy of the road ledger area map or a copy of the boundary survey map such as roads and waterways (Please attach a copy of any drawings.) A copy of the road ledger area map can be obtained at Public Works Office if the drawing has been created.Yokohama no Michi (outside site)You can check it. In addition, if a boundary survey is being conducted, a copy of the boundary survey map can be obtained in Public Works Office.)

Flowchart of procedures for self-financing construction
Procedure for self-financing

Please download "enforcement approval application such as road construction" after application about application style.
Please download "After Approval [Start / Change / Cancellation / Completion] after the application form for the start notification / completion notification.

In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Totsuka Ward Tozuka Public Works Office

Phone: 045-881-1621

Phone: 045-881-1621

Fax: 045-862-3501

Email address: to-doboku@city.yokohama.jp

Return to the previous page

Page ID: 981-184-655

Menu of ward

  • LINE
  • Twitter
  • Instagram
  • YouTube