About sewer self-financing construction
Last Updated January 4, 2024
What is Sewerage Self-Construction?
Sewerage self-financing construction is construction that person except Yokohama-shi performs construction about sewer facilities on public roads at their own expense.
In order to carry out self-financing work, you must submit an application for approval of construction of sewerage facilities to the Public Works Office and obtain approval from The Mayor of Yokohama. (Yokohama City Sewerage Ordinance, Article 16 and 27)
Application for self-financing construction
Fill out the application form with required items and attach required documents toPublic Works Office.
Application form download: Environmental Planning Bureau (Sewer self-financing construction) homepage
(It is also distributed in Public Works Office. For more information about required documents, please contact Public Works Office.)
The following documents (1 to 6) are usually attached for the installation pipe self-financing work. (Please contact us for more information.)
1. Guide Map
Copy of house map, etc.
2. Layout diagram
What shows the exterior of the building and the position of the mounting pipe
3. Floor plan
The extension of the mounting pipe is written from the inside of the basin to the center of the main pipe. First decimal point (in mile units)
Refer to installation pipe laying diagram of Yokohama-shi sewer design standard figure (pipe kyo) (we can download from sewer construction-related document. (Environmental Planning Bureau page) )
4. Longitudinal View
The extension of the mounting pipe is written from the inside of the basin to the center of the main pipe. First decimal point (in mile units)
Refer to installation pipe laying diagram of Yokohama-shi sewer design standard figure (pipe kyo) (we can download from sewer-related document. (Environmental Planning Bureau page) )
5. Excavation cross section
Compatible with the pavement type at the point. Please check with Public Works Office.
6. Copy of Application for Confirmation of Drainage Equipment Plan
A set of duplicates with a confirmation mark.
Notification of start of self-financing construction
If you have received a letter of approval from Public Works Office, start construction of sewerage facilities, etc., please submit it to Public Works Office along with a schedule to registration form.
Application form download: Environmental Planning Bureau (Sewer self-financing construction) homepage
Extension of construction period for self-financing construction
When we are going to extend construction period for unavoidable reasons, we must submit construction period extension registration form such as public sewerage facility construction to the mayor with schedule. (Yokohama City Sewerage Ordinance, Article 17, Paragraph 5)
The term "unavoidable reason" here is, in principle, the following cases.
- When negotiations with local residents are difficult and construction is delayed.
- When construction is delayed due to relocation, cut, protection, etc. of underground buried objects, etc.
- When an unexpected accident occurs at the design stage of soft ground, spring water, etc., causes a change in the construction method, etc., and the construction is delayed.
- When construction is delayed due to natural disasters, land changes, etc.
Application form download: Environmental Planning Bureau (Sewer self-financing construction) homepage
Changes in self-financing construction
When we change construction periods for unavoidable reasons or are going to change facility contents at the time of approval application, we must submit change registration form such as public sewer facility construction work to the mayor. (In the case of minority, it will be corrected in the shogun. Please contact us for more information.
Application form download: Environmental Planning Bureau (Sewer self-financing construction) homepage
Notification of completion of sewer self-financing construction, inspection
Applicants must submit the completion of construction of public sewerage facilities to the Public Works Office in charge of completion of construction of public sewerage facilities, etc. to the relevant registration form promptly and undergo a completion inspection.
Application form download: Environmental Planning Bureau (Sewer self-financing construction) homepage
The following documents (1 to 5) are usually attached for the installation pipe self-financing work. (Please contact us for more information.)
- Guide map
Copy of house map, etc. - Ledger offset diagram
Public sewer ledger figure information "Daichan map" (outside site) - Floor plan
The extension of the mounting pipe is written from the inside of the basin to the center of the main pipe. First decimal point (in mile units) - Longitudinal View
The extension of the mounting pipe is written from the inside of the basin to the center of the main pipe. First decimal point (in mile units) - Construction photo
If there is no defect in the contents of the self-financing construction (if it can be taken over as a facility in Yokohama City), after completion inspection, a certificate of completion inspection (the one with the mayor's seal or Public Works Office seal) will be issued to the applicant. Will be