About application procedure of road self-financing construction
Last Updated May 28, 2024
About road self-financing construction
What is road self-financing construction?
When a person other than the road manager performs construction related to the road, it must be approved by the road manager (Article 24 of the Road Law).
Unauthorized private property on the road premises or changing the shape of the road is prohibited by law.
For example, "We have built a new garage. There is a step from the road, so let's place a scratching block." ・This is not good. In such a case, it is necessary to perform road self-financing construction (cut down construction).
In addition, about application style, we can obtain in homepage "road self-financing construction (Article 24 application)" of City of Yokohama, Road and Highway Bureau administration section (external link).
Application details for main road self-financing construction
1.The following works related to vehicle entry into the parking lot
Sidewalk, L-shaped gutter, curb devaluation work, U-shaped gutter cover, rehabilitation work for vehicles for catchment basin lids, removal of guardrails and car stops, relocation work
Logging of street trees, replanting work, relocation of road lighting (needs consultation with the Road and Highway Bureau Facility Division in advance), relocation of curve mirrors
2.Road maintenance work associated with development and residential land development
3.Construction loading road (when the sidewalk is cut down and used as a construction vehicle approach for construction work, etc.)
4.In addition, construction to make changes to road structures
Documents to be submitted
1.Documents to be submitted at the time of application
We use "enforcement approval application such as road construction" (word: 20KB).
Even if there is no seal in the applicant column of the application form (the applicant will be the employer). In principle, the contractor must be a contractor licensed by the Construction Business Law.
In addition, please attach the following [attached documents] to the road construction approval application form and make two copies.
⇒Please refer to "Application for Enforcement Approval of Road Construction (Example)" (PDF: 147KB) for description example.
[attached documents]
(1) Guide map <Specify location on the map>
(2) Floor plan <illustrate the construction site and construction details on the entire site>
(3) Vertical crossing diagram <Specify crossing of sidewalk, vertical gradient, etc.>
"Simple drawings for entering facilities" (word: 474KB) can be obtained on the website.
⇒Please refer to "Simple drawing for entering facility (example)" (PDF: 386KB) for description example.
(4) Structural diagram
Road Structure Standard Maps (City of Yokohama, Road and Highway Bureau)
⇒L-shaped gutters, U-shaped gutters, asphalt concrete pavement, ground boundary blocks, etc.
“Yokohama City Sewerage Design Standard Map (Tube)” (Yokohama City Sewerage River Bureau, Green Environment Bureau)
⇒LU-type gutters, LO-type gutters, rainwater basins (city culverts), etc.
※"Rainwater basin margin (performance regulation type)" (PDF: 271KB), "Rainwater basin lid (performance regulation type)" (PDF: 418KB)
When replacing the existing concrete lid, use the rainwater basin lid (Type 3).
"Collection of park green tract of land facility standard figure" (Yokohama-shi sewer river bureau, green environment bureau)
⇒Planting, Torii struts, etc.
(5) Current status photo <Mark the construction site so that the entire construction area can be understood.>
(6) Copy of road ledger area map or copy of boundary investigation map such as road waterway
⇒It can be obtained from the ledger system in Public Works Office or from the road ledger map information "Yokohama no Michi" (outside site). The boundary survey map for roads and waterways is available in Public Works Office if the boundary survey has been conducted.
※If necessary, you may be required to submit "Consent registration form of the owner of the adjacent land" (word: 26KB).
⇒For example, please refer to "Consent registration form of the owner of the adjacent land of the application (Example)" (PDF: 120KB).
※In addition to the above, you may be asked to submit books that Public Works Office deems necessary.
2.Documents to be submitted after approval
We use "notice of [start, change, cancellation, completion] such as road construction" (word: 27KB).
[Start, change, cancellation, completion] Please indicate 0 in one of the applicable items.
(1) Notification of start <no seal required> must be submitted before construction.
(2) Notification of change <no seal is required> must be submitted as an attached book that shows the details of the change.
(3) Please submit a notice of cancellation <no need for seal> when you cancel your own construction. In addition, please attach original of enforcement approval letter of advice such as road construction.
(4) Notification of completion <no need for seal> must be submitted as attached books with guide maps and construction photographs (before, under construction, and completed). In addition, when there is place where road boundary mark was removed and restored, please submit copy of road ledger area map or copy of boundary investigation figure such as road waterway.
3.Other documents to be submitted
When you withdraw application before approval, please submit "report of withdrawal such as road construction" (word: 26KB).
Reference Materials
(1) “Guide to Road Self-financing Construction Application” (Road and Highway Bureau Management Division)
(2) "Information on Procedures for Road Self-financing Construction" (Public Works Office Aoba) (PDF: 1,579KB) shows the flow of road self-financing construction applications and samples of application creation.
(3) "Examination and procedures for removing street trees (cutting and planting) in road self-financing construction" (Public Works Office Aoba) (PDF: 514KB) shows the procedures for considering removing street trees along with sidewalk devaluation work. Please check the following three points.
A. "We are considering removing street trees" (Reference) (Public Works Office Aoba) (Word: 24KB) shows a sample of "news" posted on the street trees to inform nearby people before the approval of self-financing construction.
B. The “Notice of Removal of Street Trees” (Reference) (Public Works Office Aoba) (Word: 21KB) shows a sample of “Notices” posted on the street trees when it is unavoidable to remove street trees due to road self-financing.
C. When the replanting of the street trees is completed, please submit the "Street Tree Replanting Completion Report" (Public Works Office Aoba) (Excel: 12KB) along with the notification of completion of road construction. At that time, a map of the replanting position is also required.
Others
(1) We cannot answer the construction cost of road self-financing construction.
(2) We may comprehensively judge the necessity of performing road self-financing construction, the rationality of the design and implementation plan, and whether there is a problem in the road manager, and dispose of disapproval.
You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
Inquiries to this page
Aoba Ward Aoba Public Works Office
Telephone: 045-971-2300
Telephone: 045-971-2300
Fax: 045-971-3400
Email address: ao-doboku@city.yokohama.lg.jp
Page ID: 236-602-647