About temporary use of public sewer (Naka Ward)
Last Updated January 25, 2024
What is the temporary use of public sewers?
When we perform the following drainage such as construction drainage and use public sewer temporarily, please submit public sewer temporary use permission application, and please receive permission of The Mayor of Yokohama. (Yokohama City Sewerage Ordinance, Article 17, Paragraph 3)
(1) Spring water, rainwater, and construction drainage associated with civil engineering and construction work. (For spring water and rainwater, when using a pump with a kettle area)
(2) Drainage from temporary toilets and hand-washing areas installed in temporary offices
(3) Accumulated water from caretaker holes for telegraph telephone, electricity, gas, etc.
(4) Sewage drainage associated with other construction work.
In addition, when applying, drainage methods etc. must conform to the standards. In addition, waste equivalent to industrial waste cannot be drained.
Drainage method
The drainage method (connection method to the sewer) is as follows.
(1) When discharging in a combined area, it flows directly into the connecting basin.
(2) When discharging in a diverted area, let it flow directly into the sewage connection basin.
(3) Drainage associated with construction on the road (including underground) can be connected to the human hole by laying the mounting pipe and flow in.
However, please consult with Public Works Office about connection position, construction method, restoration method, etc.
(4) If there is no connection basin on or near the site, apply for self-financing at Naka Public Works Office, install the connection basin and mounting pipe, and submit an application for temporary use.
Structure of drainage facilities, etc.
When draining construction drainage, etc., install drainage facilities as follows. (Excluding Temporary Office Miscellaneous Drainage and Temporary Toilet Drainage)
(1) Public sewerage facilities, road facilities, etc. that do not interfere with traffic.
(2) In the drainage facility, install a sedimentation tank that meets the following criteria.
・A rectifier plate, cough, etc. will be provided so that no disturbance by running water will occur.
・The sedimentation tank has two or more tanks
・The average flow speed is 0.3 m/s or less in principle.
・In principle, stay time is 30 seconds or more.
・Mud can be more than 60cm
(3) When discharging alkaline or acidic sewage, set up a neutralization tank and adjust it before releasing it. In principle, the neutralization tank must have a function to automatically stop the power pump when the water quality exceeds the standard value.
(4) In principle, the sedimentation tank shall have a structure that can measure the flow rate.
Certification of water quality standards and amount of wastewater
In addition to those listed in the following table, the water quality of drainage for construction is based on the ordinances related to the conservation of the Yokohama City Living Environment and the Yokohama City Sewerage Ordinance.
Water quality should be inspected at any time, and appropriate management should be performed to comply with legal standards.
Items | Criteria |
---|---|
Hydrogen ion concentration (hydrogen index) | 5.8 or more 8.6 or less |
Biochemical Oxygen Demand | 25(mg/L) |
Chemical oxygen demand | 25(mg/L) |
The mass of suspended matter | 70(mg/L) |
Normal hexane extract content | 5(mg/L) |
Appearance | There must be no color or turbidity that significantly changes the accepted water or that increases turbidity. |
Odor | Do not contain anything that causes odor to the accepted water. |
If you violate laws and regulations or the above-mentioned standards and permission conditions, or if the city deems it necessary, you may rebuild, relocate or remove drainage facilities. In this case, the cost will be borne by applicant.
If the pipeline is blocked or damaged due to effluent such as construction drainage, restoration work costs for the facility will be collected. However, if there is an application for self-financing work from the causal person, the causal person must carry out the restoration work.
Certification of drainage and sewerage usage fees
Environmental Planning Bureau Accounting and Management Division Sewerage Fee (045-671-2826) is responsible for determining the amount of wastewater and setting the sewerage usage fee. Please pay the sewerage fee by delivery letter of advice issued by Motoichi.
Permit application and notification procedure
Please fill out the application form with required items and submit three copies to Public Works Office with required documents at least 7 days before release.
・Public sewer temporary use permission application PDF (PDF: 78KB), Word (word: 13KB)
・Estimated Total Drainage Statement Excel (Excel: 17KB)
You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
Inquiries to this page
Naka Ward Naka Public Works Office
Telephone: 045-641-7681
Telephone: 045-641-7681
Fax: 045-664-6196
Email address: do-nakaiken@city.yokohama.lg.jp
Page ID: 797-471-118