- Yokohama-shi Top Page
- Kanazawa Ward Top Page
- Living and Procedures
- Community Development and Environment
- Public Works Office
- About sewer, river
- About temporary use of public sewer
Here's the text.
About temporary use of public sewer
Last Updated July 31, 2024
What is the temporary use of public sewers?
When we perform the following drainage such as construction drainage and use public sewer temporarily, please submit public sewer temporary use permission application, and please receive permission of Mayor Public Works Office. (Yokohama City Sewerage Ordinance, Article 17, Paragraph 3)
- Spring water, rainwater, and construction drainage associated with civil engineering and construction work. (For spring water and rainwater, when using a pump with a kettle area)
- Drainage from temporary toilets and hand-washing areas installed in temporary offices
- Accumulated water from caretaker holes for telegraph telephone, electricity, gas, etc.
- Other wastewater from construction
In addition, when applying, drainage methods etc. must conform to the standards. In addition, waste equivalent to industrial waste cannot be drained.
Application for permission
Please fill out the application form (word: 36KB) with required items and submit three copies to Public Works Office with required documents at least 7 days before release.
Drainage method
The drainage method (connection method to the sewer) is as follows.
- When discharging in a stream area, let it flow directly into the connecting basin.
- When discharging in a diverted area, let it flow directly into the sewage connection basin.
- Drainage associated with construction on the road (including underground) can be connected to the human hole by laying the mounting pipe and flow in. However, please consult with Public Works Office about connection position, construction method, restoration method, etc.
- If there is no connection basin on or near the site, apply for self-financing at Public Works Office and install the connection basin and mounting pipe, and submit an application for temporary use.
Structure of drainage facilities, etc.
When draining construction drainage, etc., install drainage facilities as follows. (Excluding Temporary Office Miscellaneous Drainage and Temporary Toilet Drainage)
- Do not rush to public sewerage facilities, road facilities, etc. and traffic.
- In the drainage facility, install a sedimentation tank that meets the following criteria.
- A rectifier plate, cough, etc. will be provided so that no disturbance by running water will occur.
- The sedimentation tank has two or more tanks
- The average flow velocity is, in principle, 0.3 m/s or less.
- In principle, stay time is 30 seconds or more.
- Mud can be more than 60cm
- When discharging alkaline or acidic sewage, set up a neutralization tank and adjust it before releasing it. In principle, the neutralization tank must have a function to automatically stop the power pump when the water quality exceeds the standard value.
- In principle, the sedimentation tank shall have a structure that can measure the flow rate.
Water quality standards, etc.
In addition to those listed in the following table, the water quality of drainage for construction is based on the ordinances related to the conservation of the Yokohama City Living Environment and the Yokohama City Sewerage Ordinance.
Water quality should be inspected at any time, and appropriate management should be performed to comply with legal standards.
Items | Treatment area | Unprocessed area |
---|---|---|
Hydrogen ion concentration | PH5 or less than 9 | HP 5.8 or higher 8.6 or less |
Suspended substances | Less than 600 ppm | 70ppm or less |
If you violate laws and regulations or the above-mentioned standards and permission conditions, or if the city deems it necessary, you may rebuild, relocate or remove drainage facilities. In this case, the cost will be borne by applicant.
If the pipeline is blocked or damaged due to effluent such as construction drainage, restoration work costs for the facility will be collected. However, if there is an application for self-financing work from the causal person, the causal person must carry out the restoration work.
Certification of drainage and sewerage usage fees
Authorization of the amount of drainage and adjustment of sewerage usage fee is performed by the Sewerage River Bureau Accounting Division sewerage usage fee charge (telephone 045-671-2826). Please pay the sewerage fee by delivery letter of advice issued by Motoichi.
Inquiries
Contact information | Phone number | Details of the inquiry |
---|---|---|
Sewerage River Bureau Sewerage River Bureau Accounting and Management Division sewerage system usage fee | 045-671-2826 | Report on the amount of wastewater and inquiries about sewerage usage fees |
Sewer River Bureau Sewer River Bureau Sewer Management Division Sewer Management | 045-671-2842 | Reading of sewer ledger map attached to application |
Sewer River Bureau Green Environment Bureau Water and Soil Environment Division Water Quality Section | 045-671-2489 | Water quality standards for public water bodies |
Resources and Waste Recycling Bureau Industrial Waste Management Section | 045-671-2513 | Industrial waste |
For inquiries other than the above, please contact Public Works Office (Tel: 045-781-2511).
Inquiries to this page
Kanazawa Ward Kanazawa Public Works Office
Telephone: 045-781-2511
Telephone: 045-781-2511
Fax: 045-781-2822
Email address: kz-doboku@city.yokohama.lg.jp
Page ID: 552-165-431