The situation of construction

December, 2020 NEW!

Scaffold came off and came to show the appearance. It almost reaches completion!

picture


November, 2020  

Scaffold came off the first floor, the second-floor part. We construct interior sequentially inside.

picture


October, 2020

Interior construction and the exterior work advance sequentially.

picture


September, 2020  

We cannot see from the outside, but interior construction and the exterior work advance.
picture

August, 2020  

Skeleton construction was completed.

picture


July, 2020  

Construction of the fourth-floor part advances.


June, 2020 

The fourth-floor construction begins.

May, 2020  

The third-floor construction advances.

May, 2020

April, 2020  

The third-floor construction begins. A lot of steel frames have been crossed.
Public hall enters 2, the third floor.

Skeleton construction the first-floor on the end of December, 2019


January, 2020

The first-floor skeleton construction began. Engineering works office and inhabitant of a ward activity support center enter the first floor.

Skeleton construction the first-floor in the first year on the end of December

※In Building Standard Act, it becomes the first floor under the ground.

September, 2019

Underground construction is pushed forward.

The end of August, 2001 basement construction

May, 2019

Stake bangs and is crowded.

The end of April, 2001 pile driving

February, 2019

The basic dismantling of old government building was over. Construction of new public hall and engineering works office will advance from now on.
The first year end of January ground improvement construction

January, 2019

We started Konan public hall and Konan engineering works office maintenance construction from October, 2018.
The basic dismantling of old Konan Ward synthesis government building advances.

The end of December, 2018 dismantling construction photograph


The whole construction process

Please see the whole progress schedule (PDF: 118KB)

Contact
Housing and Architecture Bureau facility Maintenance Division telephone: 045-671-2965

Adobe Acrobat Reader DC (old Adobe Reader) is necessary to open file of Portable Document Format.
Person who does not have can download free of charge from Adobe company.
Get Adobe Acrobat Reader DCTo downloading of Adobe Acrobat Reader DC

Inquiry to this page

Konan Ward General Affairs Department Ward Administration Promotion Division

Telephone: 045-847-8321

Telephone: 045-847-8321

Fax: 045-846-2483

E-Mail address [email protected]

Return to the previous page

Page ID: 170-522-773

We come back to the top