Top >  Approach of ward  > Planning and coordination > Kanazawa Ward synthesis Government building redevelopment

Kanazawa Ward synthesis Government building redevelopment

≪Update information≫

About redevelopment of Kanazawa Ward synthesis Government building

 Kanazawa Ward synthesis Government building is built in 1971, and approximately 40 years pass and, in addition to deterioration of facility, are the situation that does not satisfy current earthquake proofing standard.
 Therefore early redevelopment is pursued in Kanazawa Ward synthesis Government building to show function as disaster headquarters of ward at the time of disaster occurrence.
 In redevelopment of Kanazawa Ward synthesis Government building, we do with plan that we utilize current site and adjacent soft-shelled turtle park and rebuild.

Business schedule (plan)

2012 basic design, conduct design
2013 conduct design
2014 ward Government building, the fire department redevelopment construction start of construction
2015 ward Government building, the fire department redevelopment construction completion (completion)
The synthesis Government building dismantling existing in 2016
2017 public hall, parking lot, the soft-shelled turtle park maintenance construction start of construction
2018 public hall, parking lot, the soft-shelled turtle park maintenance completion (completion)
※Schedule is assumption at the present. We may change by basic design and financial status to carry out in future.

Facility placement plan

Facility placement plan

※ We locate ward office, fire department in the north side of site and are plan image to locate public hall, parking lot, park in the south side.
※ We assume basic design plan to perform and may be changed in future.

About questionnaire result

 We appreciate your cooperating with questionnaire.
 About result, please see this.

 
Questionnaire result (Portable Document Format, 533KB) about redevelopment of Kanazawa Ward synthesis Government building

  • About conduct contents of questionnaireThisPlease give me ogo *.
  • Contents of Yokohama-shi public works project evaluation screening committee (prior evaluation) and opinion detailed reportThisPlease give me ogo *.

 

About progress reports

About progress report




 

Barrier-free about exchange of opinions about becoming

 

About the held situation of neighborhood briefing session


 

      Inquiry about progress reports
      Civic Affairs Bureau area facility charging talk: 045-671-2086 FAX: 045-664-5295

 

To all of you using Kanazawa public hall

About Kanazawa public hall closing

 In Yokohama-shi, we push forward rebuilding of Kanazawa Ward synthesis Government building (public hall, ward office, fire department) now.
 Lecture halls (hall) of current public hall become closing at one time from Monday, March 14, 2016. New public hall is going to be completed after 2018 and, during then, causes inconvenience.
 We maintain "multipurpose room" (capacity: around 100 seats) and "rehearsal room" in new Government building, and all of you are going to use.


 Inquiry: Regional Promotion Division inhabitant of a ward activity support charge (the fourth floor second) telephone 045-788-7804

About the noise, vibration with rebuilding construction

 We cause all of use inconvenience in the noise, vibration with construction. I would like cooperation understanding.

 Specifically, please see the next document.
 Rebuild - to all of you using Kanazawa public hall; about the noise, vibration with construction - (Portable Document Format, 123KB)
 Progress schedule (Portable Document Format, 278KB)


Inquiry about this page
Kanazawa Ward government office Ward Administration Promotion Division Planning and Adjustment Section
〒236-0021 2-9-1, Deiki, Kanazawa-ku, Yokohama-shi
Telephone: 045-788-7729 fax: 045-786-4887
Inquiry to each section from this
Making day: June 04, 2012
The last update date: March 10, 2017
©2003-2017 City of Yokohama. All rights reserved.